Route 19 Construction Project Continues

Construction continues along Route 19 (Washington Road) between McMurray Road/McLaughlin Run Road and Connor Road/Gilkinson Road as part of PennDOT's Route 19 improvement project.

This part of the project started in May 2021 and is expected to be complete in May 2022. 

Milling and resurfacing is under way, along with concrete rehabilitation, bridge preservation, drainage and guide rail upgrades, ADA curb ramp and sidewalk improvements, signal updates, and sign and pavement marking installation. Single-lane restrictions in each direction will occur in various locations around-the-clock including weekends. 

The prime contractor is A. Folino Construction, Inc. from Oakmont, PA.

PennDOT also has a project on Fort Couch Road which is slated to end mid-August 2021.