| 1 |
Encourage
re-development of the Consol site to expand business opportunities along the
Township’s regional corridor |
Short-term |
CD, TE,
TTE |
|
| |
a |
Prepare
a feasibility analysis to identify the physical and fiscal opportunities and
constraints of owning/maintaining potential road(s) in the redeveloped
site |
|
|
|
| |
b |
Continue
discussion with property owners regarding the long-term plans for occupancy |
|
|
|
| |
c |
Work with the
site re-development team to minimize impacts of parcel access on the
surrounding roadway network |
|
|
|
| |
d |
Develop
form-based provisions to guide future development |
|
|
|
| 2 |
Explore
the feasibility of incorporating additional development for public safety
services along Washington Road |
Short-term |
AD,
CD, PW, TE, TTE, TA, BOC, PC |
|
| |
a |
Evaluate
development capacity and estimate traffic to determine signalization needs |
|
|
|
| |
b |
Create
provisions to require shared access for multiple parcels |
|
|
|
| |
c |
Develop
form-based provisions to guide future development |
|
|
|
| 3 |
Determine the
potential development capacity and accessibility of the northwestern
Boyce-Washington Road intersection for non-residential development |
Long-term |
AD,
CD, TE, TTE, TA, BOC, PC |
|
| |
a |
Evaluate
development capacity based upon presence of Duquesne Light transmission lines |
|
|
|
| |
b |
Estimate
potential traffic based upon development capacity to determine parcel access
options/signalization needs |
|
|
|
| |
c |
Depending upon
access findings, determine appropriate zoning changes |
|
|
|
| |
d |
Amend parcel
zoning designations |
|
|
|
| |
e |
Develop
form-based provisions to guide future development |
|
|
|
| 4 |
Explore the
feasibility of accommodating new and/or in-fill non-residential development
along the Painters Run Road Corridor |
Long-term |
AD,
CD, TE, TTE |
|
| |
a |
Evaluate
floodplain constraints and opportunities for parcel access |
|
|
|
| |
b |
Develop access
management strategy and land use regulations |
|
|
|
| |
c |
Determine
appropriateness of re-establishing and conserving riparian buffers |
|
|
|
| |
d |
Develop
form-based provisions to guide future development |
|
|
|
| |
e |
Update the
Township's commercial property inventory |
|
|
|
| 5 |
Prepare a Conceptual
or Specific Area Plan for the McLaughlin Run Corridor to identify future
development/redevelopment strategies, pedestrian connection additions and
site improvements |
Short-term |
AD,
CD, PW, TE, TTE, BOC, PC |
|
| |
a |
Develop a
comprehensive inventory of existing development and natural resource
conditions |
|
|
|
| |
b |
Determine
the capacity for additional civic, non-residential and recreation-oriented
development |
|
|
|
| |
c |
Evaluate
options to optimize pedestrian safety and linkages within the Corridor and
identify measures for obtaining rights-of-way (as necessary) |
|
|
|
| |
d |
Identify
and compare palette options related to potential site improvements |
|
|
|
| |
e |
Create
an opinion of probable development costs and phasing strategy related to
implementing site improvements and pedestrian connections |
|
|
|
| 6 |
Create a Civic Overlay
designation for the McLaughlin Run Corridor to establish uniform development
standards such as landscaping, bufferyards, lighting and signage |
Long-term |
AD,
CD, BOC, PC, REC, PW |
|
| |
a |
Draft detailed
overlay provisions |
|
|
|
| |
b |
Designate
overlay boundary |
|
|
|
| |
c |
Adopt provisions |
|
|
|
| Housing |
|
|
|
| 7 |
Develop provisions to
encourage and permit additional opportunities in constructing a variety of
housing products |
Short-term |
CD,
TE, TTE, AD |
|
| |
a |
Determine
districts in which the redevelopment or additional attached single-family or
multi-family land uses can occur |
|
|
|
| |
b |
Prepare specific
provisions, such as setbacks, building height, service areas,
landscaping/bufferyards and parcel access, for such land uses |
|
|
|
| |
c |
Adopt provisions |
|
|
|
| 8 |
Enable
the future development of remaining undeveloped large land tracts for a
mixture of residential and non-residential land uses |
Short-term |
CD,
TE, TTE, AD |
|
| |
a |
Evaluate
development capacity and estimate traffic to determine potential impacts to
road corridors |
|
|
|
| |
b |
Develop a Conceptual
Plan or Specific Area Plan |
|
|
|
| |
c |
Develop and
adopt a Traditional Neighborhood Development Ordinance with consideration
given to instituting form-based provisions |
|
|
|
| |
d |
Amend parcel
zoning designations |
|
|
|
| Civic
Amenities |
|
|
|
| 9 |
Develop a community-wide
gateway and wayfinding system |
Long-term |
PW, CD,
AD, TE, TTE |
|
| |
a |
Determine
desired areas for constructing gateways based upon potential locations
identified on the Civic Amenities Plan |
|
|
|
| |
b |
Determine
"types" of wayfinding (vehicular versus pedestrian) based upon
intended audiences |
|
|
|
| |
c |
Create a
consistent design theme among the gateway and wayfinding components |
|
|
|
| |
d |
Explore
potential public and/or private funding opportunities |
|
|
|
| |
e |
Develop Phasing
Strategy for constructing gateways |
|
|
|
| |
f |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| 10 |
Incorporate signage
related to the community’s historic resources into the Township’s overall
wayfinding system |
Long-term |
AD,
CD, PW, BOC |
|
| |
a |
Determine
desired areas for constructing historic signs based upon potential locations
identified on the Civic Amenities Plan |
|
|
|
| |
b |
Determine
desired facilities/points of interest to be identified by signage |
|
|
|
| |
c |
Coordinate
historic resources signage with overall pedestrian network signage |
|
|
|
| |
d |
Design specific
standard for each sign type |
|
|
|
| |
e |
Explore
potential public and/or private funding opportunities |
|
|
|
| |
f |
Develop a
phasing strategy for constructing historic resources signage |
|
|
|
| |
g |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| 11 |
Assess the diversity
of the Township recreational and leisure programs and identify program
opportunities that maintain participation among youth, family and senior
groups |
Short-term |
REC |
|
| |
a |
Create a
comprehensive inventory of past and current recreation programs including
participation rate, targeted age, fee, duration, location and staffing
commitment |
|
|
|
| |
b |
Analyze
similarities and differences between program opportunities |
|
|
|
| |
c |
Identify program
opportunities that maintain participation among youth, family and senior
groups |
|
|
|
| 12 |
Create a Township
comprehensive park, recreation and open space plan |
Long-term |
AD,
CD, PW, REC, BOC, PC, TE |
|
| |
a |
Prepare a
comprehensive facility and open space analysis to identify the extent and
locations for new facility construction, existing facilities in need of
repair, levels of compliance with current Americans with Disabilities Act
standards and obsolete facilities no longer effective to residents |
|
|
|
| |
b |
Complete a
programming assessment to identify additional opportunities for outreach to
various age levels |
|
|
|
| |
c |
Evaluate the
roles and responsibilities of administration/staff and volunteer Personnel in
relationship to facilities/equipment maintenance and programming |
|
|
|
| |
d |
Identify costs
and priorities associated with desired parks, recreation and open space
enhancements |
|
|
|
| |
e |
Identify
opportunities and challenges of financing needs and potential resources |
|
|
|
| |
f |
Develop a
prioritized implementation strategy including facilities and equipment
maintenance, programming, personnel, and fiscal management |
|
|
|
| |
g |
Prepare and
adopt Comprehensive Parks, Recreation and Open Space Plan |
|
|
|
| 13 |
Amend the Township’s
open space standards to enhance the quality, quantity and connectivity of
green space |
Short-term |
CD,
BOC, PC, REC |
|
| |
a |
Analyze
the percentage, type and quality of open space within a range of identified
neighborhoods |
|
|
|
| |
b |
Determine preferences
based upon analysis |
|
|
|
| |
c |
Amend standards
for residential development/redevelopment to reflect identified preferences |
|
|
|
| 14 |
Continue to study the
feasibility of the Community Recreation Center within the Township |
Immediate |
AD,
CD, PW, REC, TE, BOC |
|
| |
a. |
Explore the
various amenities of interest for the Recreation Center that fit within the
parameters of the community's needs and wants |
|
|
|
| |
b. |
Identify costs
associated with desired amenities |
|
|
|
| |
c. |
Develop a
timeline that identifies the relationship and parameters of approvals,
bidding and construction |
|
|
|
| 15 |
Analyze the potential
for additional fields and an active recreation area at the Boyce Mayview Park |
Immediate |
AD,
CD, PW, REC, TE, TTE, BOC |
|
| |
a. |
Develop a needs
assessment for the construction of additional fields and supporting
facilities |
|
|
|
| |
b. |
Identify and
evaluate costs associated with needed fields and supporting facilities |
|
|
|
| |
c. |
Design fields
and supporting facilities as determined by the cost evaluation |
|
|
|
| |
d. |
Create bid
documents and advertise bids for field and supporting facility construction |
|
|
|
| |
e. |
Initiate field
and supporting facility construction |
|
|
|
| 16 |
Study facilities and
space allocation for the Civic Center/Administration Building concept |
Short-term |
AD,
CD, PW, TE, TTE, TA, BOC |
|
| |
a. |
Conduct
a facility needs projection study to determine the current and future use of
the Township's Civic Center/Administration Building |
|
|
|
| |
b. |
Investigate
future use/expansion of the existing Civic Center/Administration Building
based upon the study's results |
|
|
|
| Infrastructure
and Transportation |
|
|
|
| 17 |
Evaluate
the suitability of and promote best management practices through the
competition of additional stormwater management improvements |
On-going |
CD,
PW, TE |
|
| |
a |
Develop a
stormwater management status map designating completed and proposed projects |
|
|
|
| |
b |
Prioritize
phasing of proposed projects based upon severity of run-off impacts and costs |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| 18 |
Complete improvements
of the EPA Consent Order and, as appropriate, in conjunction with surrounding
municipalities |
On-going |
PW, TE, BOC, AD |
|
| 19 |
Construct
transportation improvements at McLaughlin Run Road/McMillan Road/Lesnett Road |
Short-term |
AD, CD,
PW, TE, TA,
TTE, BOC |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 20 |
Construct
transportation improvements at Washington Road/Fort Couch Road |
Long-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 21 |
Construct transportation
improvements at Washington Road/Orr Road |
Long-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 22 |
Construct
transportation improvements at McMurray Road at Bethel Church Road/Drake Road |
Long-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 23 |
Construct
transportation improvements at Boyce Road/Millwood Drive/Morton Road |
Long-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 24 |
Construct transportation
improvements at Washington Road/Boyce Road |
Immediate to
Long-term* |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 25 |
Construct
transportation improvements at Old Washington Road/Circle Drive |
Short-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 26 |
Construct
transportation improvements at Boyce Road/Hidden Valley Drive |
Long-term |
AD,
CD, PW, TE, TTE, BOC, TA |
|
| |
a |
Determine
needs/costs to acquire/secure rights-of-way |
|
|
|
| |
b |
Determine
phasing/priority of needed improvements |
|
|
|
| |
c |
Incorporate
defined phasing into the Township's Capital Improvement Program |
|
|
|
| |
d |
Develop
schematic design drawings for improvements |
|
|
|
| |
e |
Develop
construction drawings for improvements |
|
|
|
| |
f |
Construct
improvements |
|
|
|
| 27 |
Explore the
feasibility and benefits of incorporating traffic calming policies into
development |
Long-term |
AD,
CD, PW, TTE, TE, BOC |
|
| |
a |
Explore policies
to promote traffic calming on local roads |
|
|
|
| |
b |
Identify costs
and priorities associated with desired traffic calming measures |
|
|
|
| |
c |
Incorporate, if
feasible, traffic calming preferences into the Township's Capital Improvement
Program |
|
|
|
| 28 |
Prioritize
sidewalk/bikeway segments and produce a time-schedule for their construction |
Immediate |
CD, PW,
TE, TTE, TA, BOC, AD |
|
| |
a |
Develop a
detailed plan to differentiate the locations of sidewalks, bikeways and
trails |
|
|
|
| |
b |
Determine
needs/costs to acquire/secure rights-of-way based upon the Township's overall
pedestrian network |
|
|
|
| |
c |
Prioritize
sidewalk/bikeway segments |
|
|
|
| |
d |
Incorporate
segment-specific capital improvement costs into the Township’s 5-year Capital
Improvement Program |
|
|
|
| 29 |
Construct the Central
Loop of the Township’s pedestrian network |
Long-term |
CD,
PW, TE, TTE, AD, BOC |
|
| |
a |
Develop
schematic design drawings for improvements |
|
|
|
| |
b |
Prepare detailed
opinion of probable development costs |
|
|
|
| |
c |
Develop
construction drawings for improvements |
|
|
|
| |
d |
Construct
improvements |
|
|
|
| 30 |
Construct the Northern
Loop of the Township’s pedestrian network |
Long-term |
CD,
PW, TE, TTE, AD, BOC |
|
| |
a |
Develop
schematic design drawings for improvements |
|
|
|
| |
b |
Prepare detailed
opinion of probable development costs |
|
|
|
| |
c |
Develop
construction drawings for improvements |
|
|
|
| |
d |
Construct
improvements |
|
|
|
| 31 |
Construct the Eastern
Loop of the Township’s pedestrian network |
Long-term |
CD,
PW, TE, TTE, AD, BOC |
|
| |
a |
Develop
schematic design drawings for improvements |
|
|
|
| |
b |
Prepare detailed
opinion of probable development costs |
|
|
|
| |
c |
Develop
construction drawings for improvements |
|
|
|
| |
d |
Construct
improvements |
|
|
|
| 32 |
Construct the Western
Loop of the Township’s pedestrian network |
Long-term |
CD,
PW, TE, TTE, AD, BOC |
|
| |
a |
Develop
schematic design drawings for improvements |
|
|
|
| |
b |
Prepare detailed
opinion of probable development costs |
|
|
|
| |
c |
Develop
construction drawings for improvements |
|
|
|
| |
d |
Construct
improvements |
|
|
|
| 33 |
Coordinate pedestrian
connections between the Eastern Loop and the Montour Trail with the
Municipality of Bethel Park and the Montour Trail Council |
Long-term |
AD,
CD, PW, TE, TTE, BOC |
|
| |
a |
Establish
dialogue with the Municipality of Bethel Park and the Montour Trail Council |
|
|
|
| |
b |
Evaluate
alternatives for securing/acquiring rights-of-way |
|
|
|
| |
c |
Designate
rights-of-way |
|
|
|
| 34 |
Coordinate with South
Fayette Township, the Pittsburgh Industrial Railroad, Pennsylvania Department
of Conservation and Natural Resources, the Southwestern Pennsylvania
Commission and the foundation community regarding opportunities to connect
the Township Western Loop with future regional trail projects |
Long-term |
AD,
CD, PW, TE, TTE, BOC |
|
| |
a |
Establish
dialogue with South Fayette Township, the Pittsburgh Industrial Railroad,
Pennsylvania Department of Conservation and Natural Resources, the
Southwestern Pennsylvania Commission and the foundation community |
|
|
|
| |
b |
Evaluate
alternatives for securing/acquiring rights-of-way |
|
|
|
| |
c |
Designate
rights-of-way |
|
|
|
| Natural
Resources |
|
|
|
| 35 |
Evaluate and permit
additional stormwater management techniques, such as pervious surface
treatments, and other best management practices, to minimize impacts of
future flooding throughout the Township |
Immediate |
CD,
PW, TE, AD, BOC, PC, TA |
|
| |
a |
Conduct an
evaluation of the pervious surface treatment installed at Gilfillan Park |
|
|
|
| |
b |
Identify other
civic sites where additional pervious surface treatment could be tested |
|
|
|
| |
c |
Construct
secondary tests at identified sites |
|
|
|
| |
d |
Prepare a
summary of findings and develop recommendations for consideration of
permitted techniques for inclusion in the Township's construction standards |
|
|
|
| 36 |
Amend the Township’s
provisions regarding the conservation of existing woodland resources and the
re-establishment of native species |
Long-term |
CD,
PW, TE, BOC, AD |
|
| |
a |
Identify model
conservation ordinances and preferred provisions |
|
|
|
| |
b |
Contact
municipal representatives from communities supplying model ordinances to
evaluate the effectiveness of provisions |
|
|
|
| |
c |
Examine other
communities' standards related to open space dedication |
|
|
|
| |
e |
Develop a
listing of preferred native species for use within development and
re-development projects |
|
|
|
| |
d |
Prepare and
adopt ordinance language |
|
|
|
| 37 |
Continue to promote
regulations of the Greenway Overlay and expand its locations along
significant roadway corridors |
On-going |
CD, TE |
|
| |
a |
Identify
potential corridors suitable for inclusion within the Greenway Overlay |
|
|
|
| |
b |
Adopt overlay
provisions for designated roadways |
|
|
|
| 38 |
Develop provisions for
the conservation and re-establishment of riparian buffers in order to reduce
stormwater impacts |
Immediate |
CD, TE, PW, AD, TA, BOC, PC |
|
| |
a |
Identify and
prioritize areas suitable for establishing/re-establishing riparian buffers |
|
|
|
| |
b |
Evaluate
regulations of existing riparian buffer ordinances to determine the desired
range and effectiveness provisions |
|
|
|
| |
c |
Assess the
opportunities and challenges associated with various conservation techniques |
|
|
|
| |
d |
Prepare and
adopt riparian buffer/conservation provisions as part of the Township's
zoning/subdivision ordinance |
|
|
|
| 39 |
Evaluate the successes
of abandoned mine drainage remediation efforts completed to date in the
community and determine the suitability of other related applications in the
Township |
Short-term |
AD,
CD, PW, TE, BOC |
|
| |
a |
Obtain on-going
analysis and results of the Allegheny Land Trust's Wingfield Pines pilot
project |
|
|
|
| |
b |
Inventory and
evaluate the severity of existing abandoned mine drainage areas |
|
|
|
| |
c |
Prioritize remediation efforts |
|
|
|
| |
d |
Continue
dialogue with Allegheny Land Trust and/or other resource-oriented groups to
construct additional remediation efforts |
|
|
|
| Education |
|
|
|
| 40 |
Continue to
collaborate with the Upper St. Clair School District to expand joint
opportunities for cultural, recreation and educational programming |
On-going |
AD, CD, BOC, REC, PW |
|
| |
a |
Compile
a comprehensive listing of facilities and activities that are currently
shared between the entities |
|
|
|
| |
b |
Establish
periodic (quarterly or semi-annually) meetings between the Upper St. Clair
School District and the Township Board of Commissioners to discuss joint
opportunities |
|
|
|
| Municipal
Administration and Operations |
|
|
|
| 41 |
Work with Upper St.
Clair School District to promote children’s involvement in recycling at
school and at home |
On-going |
BOC,
AD, PW |
|
| 42 |
Evaluate resident and
business participation rates in Township-sponsored programs and report
annually in a community-wide publication |
On-going |
AD,
CD, REC |
|
| 43 |
Make request forms for
resident and business vacation checks for security purposes available on-line |
Short-term |
Police,
AD, IT |
|
| 44 |
Identify opportunities
to expand/broaden customer service options related to the handling of solid
waste including specialty items such as paint cans, tires, etc. |
On-going |
PW,
AD |
|
| 45 |
Formulate and host
information events where local realtors can meet with Township Officials to
discuss current community projects and events potentially important to
prospective residents/businesses |
Short-term |
AD,
CD, BOC, REC |
|
| 46 |
Produce an annual
status report of the Comprehensive Plan |
On-going |
CD,
BOC, PC |
|
| 47 |
Hold annual Board of
Commissioner, Planning Commission and Municipal Staff Workshops regarding the
implementation of the Comprehensive Plan |
On-going |
BOC, PC,
AD, CD |
|
| 48 |
Study the impacts of
potential demographic shifts on Township property and income taxes and
develop a strategy to address potential issues |
Short-term |
AD,
CD |
|
| 49 |
Continue working with
PennDOT to coordinate thoroughfare/intersection and driveway access
improvements |
On-going |
AD, PW,
CD, TTE, |
|
| 50 |
Continue working with
Allegheny County to coordinate thoroughfare/intersection and driveway access
improvements |
On-going |
AD,
CD, PW, TTE |
|
|
|
|
|
|
*Construction
of the right-turn lane onto Boyce Road Extension (Immediate);
all other components (Long-term) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|